Creating a new project
You can create a project from the project list page.
- 1
From the sidebar, click Projects.
- 2
Click New Project in the top-right corner. The New Project dialog opens with the project form.
Fill in Project Name, Client, Project Type and Retention Method first. The Additional Info, Manage Markups, Project Team and Create buttons stay greyed out until these four are filled.
Required fields
The main form has the following required fields:
| Field | Description |
|---|---|
| Project Name | Your project's name. Maximum 60 characters. |
| Client | The client this project is for. Select from the dropdown, or click the + button next to the field to open Create New Client. |
| Project Type | How you classify this project — for example, "Commercial" or "Residential". Select from the dropdown, or click the + button to add a new one. |
| Retention Method | How retention and MCD are calculated. Options: MCD, Retention — Retention, MCD — MCD & Retention on Gross. |
| MCD Percentage | The main contractor's discount percentage. Enter a percentage from 0 to 100. |
| Retention Percentage | The retention percentage. Enter a percentage from 0 to 100. |
| Billing Method | How the project is billed. Options: Applications & Payment Notices or Direct Invoices. |
The form also has an optional Project Description field for notes about the project.
Many fields start with your company's System Defaults — Retention Method, Project Type, Billing Method, VAT Rate, MCD and Retention percentages, markups and labour rates. When you pick a client, MCD Percentage and Retention Percentage change to that client's defaults. If the client has none, both are set to 0, so check them before you save. Changing them here does not affect the client record.
Project number
By default, Project Commander auto-generates the project number using the prefix and sequence configured on the System Prefixes page.
If you need to set the number manually, tick Set project number manually and enter a number. It must contain only letters, numbers, hyphens, forward slashes, and full stops — and it must be unique. A green tick confirms the number is available. If it is already taken, the message This project number is already in use appears.
If your company does not use automatic numbering for projects, there is no tick box — you must type the Project Number.
VAT rate
Optionally select a VAT Rate from the dropdown. This sets the default VAT rate used on financial documents within the project. Click the + button next to the field to add a new VAT rate.
Additional information
Click the Additional Info button beneath the main fields to open the Additional Project Information dialog with optional details.
| Field | Description |
|---|---|
| Self Billing Project? | Tick if this is a self-billing project. Automatically ticked if the billing method is "Direct Invoices". |
| Order Number | The client's order or contract reference number. |
| Order Value | The total contract or order value. When you import an estimate or schedule of rates, this figure is replaced by the imported total. |
| Project Manager | Select from employees flagged as project managers. Click the + button to add a new one. |
| Site Manager | Select from employees flagged as site managers. Click the + button to add a new one. |
| Start Date | The date work starts. |
| End Date | The project end date. Must be on or after the start date. |
| Practical Completion Date | The expected practical completion date. Must be after the start date. |
| Final Retention Date | Automatically calculated as one year after the practical completion date. You can override it manually. |
| Address | The project's site address. Select from your site addresses, or click the + button to add one. |
| Region | The geographic region for reporting. Select from your regions, or click the + button to add one. |
Markup configuration
Click the Manage Markups button to open the Manage Project Markups dialog and set default markup percentages for the project. These values pre-fill when creating Variations and Dayworks within this project.
Daywork markups
| Field | Description |
|---|---|
| Material Markup % | Percentage markup on materials for Dayworks |
| Labour Markup % | Percentage markup on labour for Dayworks |
| Subcontractor Markup % | Percentage markup on subcontractor costs for Dayworks |
| Default Labour Rate (/hr) | Hourly labour rate in GBP for Dayworks |
Star rated markups (Variations)
| Field | Description |
|---|---|
| Material Markup % | Percentage markup on materials for Variations |
| Labour Markup % | Percentage markup on labour for Variations |
| Subcontractor Markup % | Percentage markup on subcontractor costs for Variations |
| Default Labour Rate (/hr) | Hourly labour rate in GBP for Variations |
All markup fields are pre-populated from your company's system defaults. You can override them per project.
Project team
Click the Project Team button to choose who works on this project.
- 1
Click Project Team.
- 2
Tick the people you want in the Available list.
- 3
Click the Add selected button to move them to the Assigned Team list.
- 4
Close the dialog. The team is saved when you click Create.
People whose RBAC scope is Assigned projects only can only see this project once they are in the Assigned Team list. See RBAC.
Saving the project
Click Create to save the project. Your new project opens on its Project Dashboard.
To bring in the project's estimate from Ensign, see Importing an Ensign Estimate.
Next steps
- The Project Dashboard — explore the project overview, headline cards, and charts.
- Importing an Ensign Estimate — import the project's estimate from Ensign estimating software (.zip).
- Import Wizard — import cost codes, buying lists, and schedules of rates.
- The Project List — find and filter your projects.
- RBAC — control who can see and change each project.