What a Retention Application is
Retention is the part of each payment your client holds back until the job is finished. A Retention Application is an Application for payment (APP) that claims that money back.
It has no Completed Work, Unfixed Materials, Variations or Dayworks. It only holds the retention figures.
There are two kinds:
- Retention Application — claims part of the retention now (the practical share). The rest is held back as final retention.
- Final Retention Application — claims the final retention that is left, in one go.
Where to find them
Open a project and click Applications in the sidebar under Contract Management. Retention Applications sit in the same table as your other Applications. Their numbers start with RET-. Click the number or description to open one.
On the RBAC screen, these permissions sit under Applications. You need View to see the page and Create to make a Retention Application. Changing its status or its Claimed Value needs Edit.
Before you start
- Approve your Applications first. The Retention Value (£) only adds up the retention on
ApprovedApplications. - Check the project's retention settings. The split and the dates are filled in from the project. Click Update Project to see them:
- Retention Released at Practical Completion (%) — the share you claim at practical completion. Blank means 50%.
- Practical Completion Date and Final Retention Date — under Additional Info.
Creating a Retention Application
- 1
Click New Application in the top-right corner.
- 2
Enter a Reference.
- 3
Select a Claim Date. It cannot be earlier than the claim date of the project's most recent Application.
- 4
Optionally enter a Description, External Notes and Internal Notes.
- 5
Tick Retention Application. The retention fields appear.
- 6
Check the Retention Value (£). It is the total Retention on your
ApprovedApplications, not counting Retention Applications. Change it if you need to. - 7
Check the Practical Retention Split % — the share of the Retention Value you are claiming now.
- 8
Check the Practical Retention Date and Final Retention Date. If you change the Practical Retention Date, the Final Retention Date moves to one year after it.
- 9
Click Create. You are taken to the Retention Application page.
When you click Create, the Retention Value is split in two:
- Practical Retention — the Retention Value times the split %. This is what you claim now.
- Final Retention — what is left. This stays held back until you raise a Final Retention Application.
For example, a Retention Value of £10,000 with a split of 50% gives a Practical Retention of £5,000 and a Final Retention of £5,000.
Claiming the final retention
When the defects period ends, raise a Final Retention Application to claim the rest.
- 1
Click New Application.
- 2
Enter a Reference and select a Claim Date.
- 3
Tick Retention Application.
- 4
Tick Final Retention Application. The Practical Retention Split % and Practical Retention Date fields disappear.
- 5
Check the Retention Value (£). It is the total Final Retention on your
ApprovedRetention Applications. - 6
Check the Final Retention Date.
- 7
Click Create.
A Final Retention Application claims the whole Retention Value. There is no split.
The Retention Value (£) for a final claim only counts Retention Applications that are Approved. Approve the earlier Retention Application before you raise the final one.
The Retention Application page
The header shows the number and the words Retention Application. It has a Generate Report button (choose PDF or DOCX) and the status button.
Retention Summary
The Retention Summary card shows figures for the whole project. They are the same on every Retention Application in the project.
| Figure | What it shows |
|---|---|
| Application Total | The Before Retention total of your ordinary Applications. Cancelled Applications are left out. |
| Retention Total | The retention held back on those Applications. |
| Difference | Application Total minus Retention Total. |
The claimed retention table
The table has one row for this claim.
| Column | What it shows |
|---|---|
| Reference | The reference you entered. |
| Retention Value | The Retention Value you entered. |
| Retention Split % | The Practical Retention Split %. Shows 0% on a Final Retention Application. |
| Practical Retention | The share claimed now. |
| Final Retention | The share held back for the final claim. |
| Claimed Previously | Retention already claimed on earlier Retention Applications in this project. |
| Claimed Value | What this Retention Application claims. It starts at the Practical Retention — or the Final Retention on a Final Retention Application. |
To change the Claimed Value, click the cell, type the new figure and press Enter. It locks once the Retention Application is Approved.
Status
A Retention Application moves through the same statuses as any Application.
| Status | Meaning |
|---|---|
Created | New. |
Submitted | Sent to the client. You can still change the Claimed Value. |
Approved | Agreed. The status and the Claimed Value are locked. |
To change the status, click the status button in the header and choose the new status.
How Retention Applications show on the Applications page
- Numbers —
RET-goes in front of your Application prefix, for example RET-APP-00004. The count carries on from the project's other Applications, so after APP-00003 comes RET-APP-00004. - Retention column — shows - for a Retention Application. Its retention is not added to the column total.
- Practical Retention and Final Retention columns — show the Retention Application's two shares. Ordinary Applications show - here.
- Summary cards — a Retention Application counts towards Total Claimed. A Retention Application adds its Practical Retention. A Final Retention Application adds its Final Retention.
Payment Notices and Invoices for retention
A Retention Application is not linked to a Payment Notice for you. When your client confirms the release, record it as a Payment Notice with Retention Notice ticked.
- The Payment Value fills in with the practical retention held back on your ordinary Payment Notices.
- For the last release, tick Final Retention Notice as well. It only appears once Retention Notice is ticked.
- The Payment Notice is numbered with
RET-in front, for example RET-PN-00005. - An Invoice raised from it is numbered with
RET-in front too, for example RET-INV-00001. Retention Invoices have their own count.
Next steps
- Applications — claim completed work, Variations, Dayworks and unfixed materials.
- Payment Notices — record what your client certifies, including retention releases.
- Invoices — raise the Invoice for a retention release.
- Editing a Project — set the retention split and retention dates the form fills in.
- System Prefixes — change the Application prefix that
RET-numbers build on.