What Applications are
An Application for payment (APP) is your formal claim to the client for work completed. Applications pull together completed work from the schedule of rates, unfixed materials from the buying list, and any Variations or Dayworks that have been applied to the project.
Viewing Applications
Open a project and click Applications in the sidebar under Contract Management. The table shows each Application's number, description, status, reference and Claim Date. It also shows the Before Retention, MCD, Retention and After Retention figures, and who created it and when. The Practical Retention and Final Retention columns are only filled in for Retention Applications.
Cards above the table show how many Applications are Created, Submitted and Approved, with the Total Claimed for each. The Overall Total card shows the total count, the Total Claimed and what is Outstanding.
Filter by Status or Created By.
Creating an Application
- 1
Click New Application in the top-right corner.
- 2
Enter a Reference for the Application.
- 3
Select a Claim Date. It must be on or after the claim date of the last Application created on this project. If it is earlier, you see Date must be after previous Application Date.
- 4
Optionally enter a Description.
- 5
Optionally add External Notes. These are printed on the Application report. Notes marked as default in System Notes are filled in for you. Click the notes button in the box to add more.
- 6
Optionally add Internal Notes. These are for your team only and are never printed on reports.
- 7
Optionally tick Split Labour and Material to show labour and material figures in the claim tables. See Split Labour and Material below.
- 8
Click Create. You are taken to the Application detail page.
To claim back retention instead, tick Retention Application on the same form. See Retention Applications.
The Application detail page
Across the top are four cards: Completed Work, Unfixed Materials, Variations and Dayworks. Each one is a source of work you can claim. Click a card to show its table below the cards.
Each card shows:
- Current Value — what this Application claims for that section
- Total Value — what has been claimed for that section on this Application and every Application before it
- Previous Value — what earlier Applications claimed. Click on the card to show it
The Application Total card shows the value Before Retention, the MCD and Retention taken off (in the order set on your project), and the value After Retention. Previous shows what earlier Applications claimed, and All adds this Application to that figure.
Claim Remaining and Clear All
On the Completed Work, Variations and Dayworks cards, two buttons sit at the top of the page:
- Claim Remaining — claims everything still unclaimed in that card's table
- Clear All — sets every claim in that card's table back to zero
Both ask you to confirm, and the change cannot be undone. They are not shown on Unfixed Materials, or once the Application is Approved.
Completed Work
Shows the project's schedule of rates as a tree. For each line, enter a % Claimed or a Value Claimed under This Application Totals. Enter one and the other is worked out for you. All Application Totals shows the running total across every Application.
If the project has no schedule of rates, you see No Completed Works found. Click Create Completed Work to open the Application wizard. See The Application wizard below.
Unfixed Materials
Shows buying list items that can be claimed as unfixed materials on site. Filter by Cost Code to find specific items.
Enter the number of each item on site in # Claimed under This Application. The £ Value is worked out for you. All Applications shows the running total across every Application.
Variations
Shows chargeable Variations that have been applied to Applications, with Apply to → Project or Apply to → Applications only. Revised and Cancelled Variations are not shown. If a Variation has an Agreed Value, the Value column shows that figure and you claim against it.
Each row has editable % Claimed and £ Claimed cells under This Application Totals. Enter the portion of each Variation you want to claim in this Application. Changing the percentage updates the value, and vice versa. All Application Totals shows the running total.
You cannot claim more than what is left. If a figure would take the total claimed above 100%, it is reduced to the amount remaining.
Dayworks
Shows Dayworks that have been applied to Applications, with Apply to → Project or Apply to → Applications only. Cancelled, Rejected, Archived and Voided Dayworks cannot be claimed.
It works the same way as Variations, but the editable cells are % Claimed and Value Claimed. The same limit applies — you cannot claim more than what is left.
When the Application status is Approved, all claim controls are disabled. You cannot modify claims on an approved Application.
Split Labour and Material
When Split Labour and Material is ticked, the Completed Work, Variations and Dayworks tables show extra columns. You cannot edit these figures.
| Column | Where it appears | What it shows |
|---|---|---|
| Labour Total and Material Total | Next to Value | The labour and the material in each line |
| Labour Claimed and Material Claimed | Under Labour & Material Breakdown, after This Application Totals | The labour and material claimed on this Application |
| Labour Claimed and Material Claimed | Under All Application Totals | The labour and material claimed on every Application up to and including this one |
The claimed figures follow the share you claim. For example, a line with £100 labour and £50 material, claimed at 25%, shows £25.00 Labour Claimed and £12.50 Material Claimed.
- Completed Work takes its labour and material from the schedule of rates.
- Variations and Dayworks take theirs from their items, with markup included.
- Unfixed Materials does not change.
With the split on, the Application report uses the labour and material layout for those three sections. To switch the split on or off later, choose Actions → Modify Application. You cannot change it once the Application is Approved.
The Application wizard
If your project has no schedule of rates, you can build your own completed works breakdown with the Application wizard. The wizard page is titled Create Custom CSV.
The breakdown has up to four levels:
| Level | Colour | Purpose |
|---|---|---|
| A | Blue | Root sections |
| B | Green | Subsections |
| C | Yellow | Items |
| D | Purple | Lowest level — nothing can be added under it |
- 1
Open an Application and click the Completed Work card.
- 2
Click Create Completed Work. The wizard can only be opened from this button.
- 3
Click Add Level A to add a root section.
- 4
Click on a row to add a row at the next level down, up to Level D.
- 5
Enter a Description for each row.
- 6
Enter a Total Cost on each row that has nothing under it. A row with rows under it shows their total automatically.
- 7
Click Create Custom Application.
- 8
Read the Create Completed Works? warning, then click Yes, create. You are taken back to the Applications list.
Check every description and value before you click Yes, create. Once created, the breakdown cannot be edited or removed. If you make a mistake, contact support.
Every row must have a description before you can create the breakdown. If any are empty, the wizard lists where they are.
Status and actions
An Application moves through three statuses: Created, Submitted and Approved. To change the status, click the status button in the header and choose the new status.
Once an Application is Approved it is locked:
- Its claims, details and status cannot be changed.
- Modify Application is no longer offered.
- It cannot be deleted.
If you need to change an approved Application, contact support.
From the Actions dropdown you can:
- Generate Report — choose Claimed Only or Claimed & Unclaimed, each at All Levels or Root Levels. Under Include Sections, tick Completed Works, Unfixed Materials, Variations and Dayworks as needed, then click PDF.
- Modify Application — edit the Reference, Claim Date, Description, External Notes, Internal Notes and Split Labour and Material. Not available once the Application is
Approved. - Link with Issue — associate the Application with a project action
- Cancel Application — cancel the Application (unavailable if already approved or cancelled)
Next steps
- Payment Notices — issue Payment Notices with MCD and retention deductions.
- Retention Applications — claim back the retention held on your Applications.
- Variations — manage scope changes that feed into Applications.
- Dayworks — manage Daywork records that feed into Applications.