What subcontractor Payment Notices are
A subcontractor Payment Notice certifies the amount to be paid to a subcontractor. It is raised against one approved Subcontractor Application and tracks which items have been certified for payment.
Viewing subcontractor Payment Notices
Open a project and expand Subcontractors in the sidebar, then click Payment Notices. Payment Notices are grouped under the Subcontractor Application they certify. Click the arrow next to an Application to show or hide its Payment Notices.
The columns are #, Reference, Subcontractor, Status, Application Value, Net Value, MCD Value, Retention Value and Total, plus Created By and Created On.
- The Application row shows its number, reference, subcontractor, status and Application Value — what the subcontractor claimed. Its Total is the total certified across its Payment Notices.
- Each Payment Notice row shows its Net Value, MCD Value, Retention Value and Total. Click its number to open it.
Filter by Subcontractor, Status or Created By.
Creating a subcontractor Payment Notice
- 1
Click New Payment Notice in the top-right corner.
- 2
Select the Application. Only
ApprovedApplications are listed. - 3
Enter the Reference.
- 4
Set the Date.
- 5
Check the MCD % and Retention %. They fill in from the order.
- 6
Set the Practical Completion Date. The Final Retention Date fills in one year later — change it if needed.
- 7
Click Create.
If no Application has been approved yet, you see No Applications found. Approve the Application first — see Subcontractor Applications.
Summary cards
The detail page shows three cards at the top:
| Card | Shows |
|---|---|
| Total Value | The total certified on the lines, before deductions |
| MCD Value | The MCD deducted, added up from each line |
| Retention Value | The retention deducted, added up from each line |
Certifying items
On the detail page, each item from the subcontractor's Application is listed. While the Payment Notice is Pending, enter the PN % or PN Value on each line, or use the bulk actions:
- Certify All — certifies the full amount the Application claimed on every line, less anything certified before
- Clear All — resets all certifications
Then submit and certify the Payment Notice.
- 1
Click the status button at the top of the page and choose Submitted. The lines lock.
- 2
Click Certify.
- 3
Check the figures in the form.
- 4
Click Post.
The Payment Notice is now Certified, posted to the project budget, and locked.
Certify is greyed out while the Payment Notice is Pending. If you choose Submitted before entering any values, you are asked to confirm first.
To change the lines after submitting, set the status back to Pending. The lines unlock again.
Generating a report
You can generate a report from Actions > Generate Report at any status.
Status workflow
| Status | Meaning |
|---|---|
Pending | Payment notice created — you can change the lines |
Submitted | The lines are locked, ready to certify |
Certified | Items certified for payment and posted to the budget — locked |
Once the Payment Notice is Certified, it can no longer be changed. The status is fixed, and Modify Payment Notice is no longer shown under Actions.
Sending to Xero or Sage
If your company has connected Xero or Sage on the Connections page, the Payment Notice is sent to your accounting software when it is certified.
- To send it again, click Sync to Xero or Sync to Sage in the header. After the first sync, the button reads Re-sync to Xero or Re-sync to Sage.
- A coloured dot on the button shows the result — green once the sync has worked, red if it failed.
- If a sync fails, a Sync to … failed window tells you why. Project Commander may try again by itself for a few minutes. If not, click Try again.
- Once synced, the header shows the provider's logo with Connected.
Next steps
- Subcontractor Applications — manage the claims that Payment Notices certify.
- Subcontractor Invoices — raise an Invoice from a certified Payment Notice.
- Subcontractor Orders — manage Subcontractor Orders.