What Delivery Notes are
A Delivery Note (DN) records goods delivered to site against a firmed Purchase Order. Each Delivery Note references a specific PO and tracks which items have arrived and in what quantities.
Viewing Delivery Notes
Open a project and click Delivery Notes in the sidebar under Procurement. The list is grouped by Purchase Order — each PO appears as a parent row showing the supplier, order value, total delivered value, and outstanding value. Expand a PO to see its individual Delivery Notes.
Creating a Delivery Note
- 1
Click New Delivery Note in the top-right corner.
- 2
Select the Purchase Order this delivery is for. Only firmed orders that still have something left to deliver are listed.
- 3
Enter the Reference — the supplier's Delivery Note number.
- 4
Check the Date Delivered. It starts on today. Change it if you need to.
- 5
Optionally add Internal Notes. These are not printed on reports.
- 6
Click Create. You are taken to the Delivery Note detail page.
If no firmed order has anything left to deliver, the window shows No Purchase Orders found and a Go to Purchase Orders button instead of the form.
Marking items as delivered
On the detail page, each line from the Purchase Order is listed. Type the quantity that arrived into the This Delivery column for each line. Previously Delivered and Ordered Quantity are shown alongside, so you can see what is still to come.
You can't enter more than is still to be delivered. A higher figure is reduced to the quantity outstanding.
You can also use the buttons at the top of the page:
- Deliver All — fills in every line with the quantity still to be delivered
- Clear All — sets every line back to zero
- Mark as Delivered — finalises the Delivery Note
If the status is still Pending when you click Mark as Delivered, a window warns "No Items have been marked for delivery". If you carry on, the Delivery Note is marked Delivered with nothing on it, and you can no longer change its quantities.
Recording a delivery from the main sidebar
You can record a Delivery Note without opening the project first. This helps when deliveries for several projects arrive together.
- 1
Click Global Delivery Notes in the Company group of the main sidebar. The Create Global Delivery Note window opens.
- 2
Click Purchase Order and choose the order. Type to search by PO number, project or supplier.
- 3
Enter the Reference — the supplier's Delivery Note number.
- 4
Check the Date Delivered. It starts on today.
- 5
Optionally add Internal Notes. These are not printed on reports.
- 6
Click Create. The new Delivery Note opens inside its project.
- 7
Mark the items that arrived, or click Deliver All.
- 8
Click Mark as Delivered.
How this differs from creating a Delivery Note inside a project:
- You choose the Purchase Order first. The list holds firmed POs from every project that are not yet fully delivered. The project is taken from the PO you pick.
- You go straight on to the next delivery. After Mark as Delivered, you return to the Dashboard and the Create Global Delivery Note window opens again.
Everyone sees Global Delivery Notes in the sidebar, but you still need the Create permission for Delivery Notes on the PO's project. If no orders are waiting for delivery, the window shows No Purchase Orders available.
Status workflow
The first three statuses update by themselves as you enter quantities:
| Status | Meaning |
|---|---|
Pending | Delivery Note created, but no quantities entered yet |
Partial | Quantities entered, but at least one line is less than its full Ordered Quantity |
Fulfilled | Every line's This Delivery matches its full Ordered Quantity. Click Mark as Delivered to finish |
Clicking Mark as Delivered finishes the note:
| Status | Meaning |
|---|---|
Delivered | Finished. Set when the status was Fulfilled (or Pending — see the warning above) |
Partially Delivered | Finished. Set when the status was Partial |
Revised | A revision has been created |
Cancelled | Delivery Note cancelled |
The status dropdown is disabled when the status is Delivered, Partially Delivered, or Revised.
A delivery only counts in the Delivered column on Budgets once you click Mark as Delivered — that is, once its status is Delivered or Partially Delivered.
Other actions
The Actions menu on the Delivery Note page also has:
- Modify Delivery Note — change details such as the Supplier Reference, Date Delivered or Internal Notes. Available until the note is
DeliveredorPartially Delivered. - Revise Delivery Note — marks this note
Revisedand opens a new copy, with /R1 added to its number and the quantities cleared. Not available while the note isPending. You can't revise it once an Invoice Checking record for the same order lines has been markedInvoiced. - Cancel Delivery Note — cancels the note.
You can't cancel a Delivery Note that has Goods Return Notes against it. Cancel the returns first.
Link with Issue
From the Actions dropdown, choose Link with Issue to attach this Delivery Note to a project Action. Search by issue number or title. Once linked, the Action's linked-records list shows this Delivery Note. Each Delivery Note can be linked to a single Action.
Next steps
- Goods Return Notes — record returns against delivered items.
- Invoice Checking — verify supplier Invoices against deliveries.